Client information:

Highways England
The Cube
199 Wharfside Street
Birmingham
West Midlands
B1 1RN

Project Information:

Administrated from: Leeds
Contract location: Area 12 ASC
Value: £492,000.00 (one off)
Sector(s): Highways England, Highways England > Area Works (ASC), Local Authority, Local Authority > Improvement works
Type(s) of work: Road Closure & Diversion
Short description: Off peak/ weekend slip road & carriageway closures alond with gatemen, marshalls or convoy working

Scope of Works: Provision of temporary traffic management for 20no. short duration resurfacing schemes across Highways England Area 12. TM consisted of off peak/weekend slip road and carriageway closures with gatemen and marshals, or convoy working.

Interface Management:

  • Coordination with other specialists, our supply chain, the term maintenance provider, police etc.
  • Managing multiple works accesses and egresses, and multiple entry points for members of the public - e.g. A1(M) SB and NB Ferrybridge with M62 EB and WB approaches- weekend closures
  • Road space booking and liaison with Regional Control Centre
  • Dedicated Supervisor to attend weekly programme and progress meetings
  • Active participation in site’s safety initiatives including HGV/wide load detection radar system on the double diversion routes for the A1(M) SB and NB Ferrybridge with M62 EB and WB approaches to prevent errant HGVs striking a low bridge on the small vehicle only route. Bodycams used by marshals on several closure points to help reduce incidents with members of the public

 
Performance Highlights:

  • Zero HAIL complaints relating to the standards of traffic management deployed.
  • MST scores for this package: Reporting period Jan 2015- Sep 2015
Key Indicators Feb-15 May-15 Jul-15 Sep-15
Reporting Period Report 1 Report 2 Report 3 Report 4
Product 8 8 8 8
Service 7.5 8 8 8
Right First Time 8 8 8 8
Cost 8 7 4 8
Time 6 10 8 8
Health & Safety 8 8 8 8
Overall 7.7 8.2 7.3 8

 
Note. Score 8 = Highly Satisfied - 'All aspects are satisfactory and there is evidence that several aspects are exceeding expectation. Supplier is successful in identifying best practice'